Entellisys Low Voltage Switchgear

Chapter 4. Equipment Installation


Breaker Hoist

Fig. 4-18 shows the breaker hoist assembled on a switchgear

lineup. The hoist is shipped in a separate carton completely

assembled, Fig. 4-19.

Before attempting to install the hoist assembly on the

switchgear equipment, it is necessary to remove the runner

guide from the hoist carriage as shown in Fig. 4-20. Do not

dispose of this guide since it must be reinstalled after

mounting the hoist on the equipment.

NOTE: Maximum recommended lifting capacity is 700

lbs.

NOTE: La capacité maximale recommandée de

soulèvement est de 700 livres.

Fig. 4-18. Breaker hoist assembly

Fig. 4-19. Carton containing breaker lifting device





Fig. 4-20. Removal of hoist runner guide