63

Entellisys Low Voltage Switchgear

Chapter 9. Maintaining the Switchgear

ATTENTION: Assurez-vous que la condition ayant causé

le surchauffement a été corrigée avant de mettre sous

tension.

2.

Check all bolts that hold cable terminals to the

connection bars for tightness.

3.

Check the neutral bus and ground bus connection and

mounting bolts for tightness.

4.

Check that all secondary control wiring connections

are tight and that all control cabling is intact.

9-5 Overall Switchgear

Make the following checks on the complete switchgear

equipment.

1.

Clean and inspect all painted surfaces and retouch

where necessary.


2.

Check to see that all anchor bolts and other structural

bolts are tight.


3.

Check that all breaker and instrument compartment

door latches operate properly.


4.

If the switchgear is equipped with heaters, check to see

that all heaters are energized and operating.


5.

For exterior vent openings in equipment furnished with

air filters, the foam filter elements should be removed

and washed in warm soapy water, rinsed, and

reassembled at least annually. Elements should be

inspected before re-assembly and replaced if any signs

of deterioration are evident.




9-6 Paint Refinishing

Indoor switchgear is finished with ANSI-61 gray acrylic

enamel paint. To refinish damaged areas, remove all loose

paint, rust, scale, oil or grease. Sand any scratches smooth

using 220 grit paper or finer.

—Apply a coat of acrylic enamel primer with a viscosity of

approximately 24-32 seconds using a #2 Zahn cup. Reduce

with thinner if needed. Air-dry the primer for a minimum of

30 minutes, and then apply the finish color coat of acrylic

enamel. The topcoat should be applied within 24 hours for

best adhesion.

—If the area is to be spray-coated, thin the acrylic enamel.

This thinning should only be necessary if the paint was

received in a five-gallon drum or more. The recommended

viscosity for the enamel topcoat should be 24-32 seconds with

a #2 Zahn cup. Both the primer and paint should be applied

only when temperature is above 55 degrees Fahrenheit.

—Application of special paint will be per the manufacturer’s

Product Data Sheet that includes instructions on thinning

and application.

9-7 Circuit Breaker Lifting
Mechanism

Under normal conditions, no special maintenance procedures

or lubrication is required for this device. If the cable is

abraided under any condition, it should be inspected for

broken strands or other damage and replaced if necessary.