Entellisys Low Voltage Switchgear

Chapter 4. Equipment Installation

The ground bus is mounted directly on the rear upright

channels.

NOTE: It is particularly important that the ground bus be

connected first since it provides an integral ground for all

the equipment. It must also be connected to the station

ground prior to proceeding with the installation.

NOTE: Il est particulièrement important que la barre

omnibus de mise à la terre soit branchée en premier, étant

donné qu’elle fournit une mise à la terre intégrale à tout

l’équipement. Elle doit aussi être branchée à la mise à la

terre du poste avant de procéder à la installation.

A 4/0 AWG cable connector is located in the bottom of the

transition section (or in the incoming line compartment if a

transition section is not included) for terminating the

purchaser's cable connection to ground. The specific location

of the station ground connection is shown on the site floor

plan drawing and in the frontview drawings supplied with

the equipment. All grounding of the switchgear should be in

accordance with National Electrical Code.


Fig. 4-9. Plan view of ground bus splice installation


Fig. 4-9 illustrates the installation of the ground bus splice

plate across a shipping split. In addition to the bolted

fastening of the splice plate to the two ends of the ground

bus, self-tapping 1/4-20 bolts pass through the splice plate

and ground bus stubs, and thread into the equipment frame.

These bolts should be fastened with a torque of 7-9 ft-lbs.








If a GE transformer (rated above 750 kVA) is present in the

line-up, a ground bar located in the transition compartment,

Fig. 4-10, is provided for connection of the transformer

ground pad to the equipment ground termination point.

Fig. 4-10. Flange opening on a transition section to a GE transformer

(above 750 kVA)

As shipped, the ground bar is mounted so it does not protrude

beyond the outer surface of the equipment. When the

equipment is installed in its final location, the ground bar

must be reassembled using the outer bolt holes in the

horizontal ground bus spanning the width of the transition

compartment. In this mounting location, the offset portion of

the ground bar will permit connection to the transformer

ground pad with the 1/2-13 bolt assembly supplied with the

switchgear equipment. If an optional floor plate is supplied

for the transition compartment, it will be necessary to remove

the floor plate to permit relocation of the ground connection

bar.