7.7 Dialysis procedure

833 IC Liquid Handling Unit / Instructions for Use 8.833.1003

67

7 Rinse dialysis system

At the end of the measurements immerse sample aspiration

tubing 16 in the acceptor solution.

Start the peristaltic pumps in «IC Net» by setting the remote

line 1 (833 Pump Unit) and remote line 2 (833 Dialysis Unit) in

the window of the 819 Detector.

Rinse the dialysis system with acceptor solution for approx.

10 min and then switch off the pump again.

8 Closing down the dialysis system

To shut down the dialysis cell the acceptor and sample

channels must be rinsed with ultrapure water for approx. 10

min. The inlet and outlet tubing is then screwed off from the

dialysis cell and openings 49, 50, 51 and 52 (see Fig. 15) are

each closed with a 6.2744.060 Blank stopper.

If the dialysis system is not to be used for a long time then the

dialysis membrane must be removed and the cell has to be

cleaned, see Section 9.2.7.1 and Fig. 15.


Advertising