Chapter 4: System Installation

4.2 Cable Parts List

Table 4-1. Cable Parts List

Part Description

Part of

IEEE 1394 Cable, 4.5 M

All systems

XSYS Cable (AIB), 4.5 M

AIB 

eAIB XSYS Cable (eAIB), 4.5 M

eAIB

eAIB XSLV Adapter Cable (eAIB),
250 mm

AIB to eAIB upgrade

Front Panel Cable

Front panel

T1/T2 Pendant Adapter Cable

Optional T2 pendant

T20 Pendant Adapter Cable

Optional T20 pendant

Power Cable Kit - contains 24 VDC
and AC power cables

Available as option

XIO Breakout Cable, 12 inputs/
8 outputs, 5 meter

Available as option—
see XIO Breakout
Cable on page 94

Y Cable, for XSYS cable connections
to dual robots - attaches at the
controller for an eAIB system

Available as option --
see the

Dual Robot

Configuration Guide

.

4.3 Installing the SmartController Motion Controller

Refer to the

Adept SmartController User’s Guide

for complete information on installing the Adept

SmartController. This list summarizes the main steps.

1. Mount the SmartController and front panel.

2. Connect the front panel to the SmartController.

3. Connect the pendant (if purchased) to the SmartController.

4. Connect user-supplied 24 VDC power to the controller.

Instructions for creating the 24 VDC cable, and power specification, are covered in the

Adept SmartController User’s Guide

.

5. Install a user-supplied ground wire between the SmartController and ground.

4.4 Connecting User-Supplied PC to Robot

The Adept Quattro robots must be connected to a user-supplied PC for setup, control, and
programming. The user loads the Adept ACE software onto the PC and connects it to the robot
via an Ethernet cable.