5 operation, 1 operating states, Danger – KACO Powador XP100-HV User Manual

Page 22

Advertising
background image

Page 22

Operating Instructions Powador XP100-HV

I n s t a l l a t i o n / S t a r t - u p

ON OFF

Fault

History

Statistics

Setup

701.0V

380.0V

75.8kW

79.0kW

45.0°C

Date/Time

Figure 12: MMI screen

5.5 Operation

DANGER

Lethal voltages are still present in the terminals and lines of the inverter even after the
inverter has been switched off and disconnected!

Coming into contact with the lines and terminals in the inverter will cause serious injury or death.

Only authorised electricians who are approved by the supply grid operator may open, install and
maintain the inverter.

Keep all doors and covers closed when the unit is in operation.

Do not touch the lines and terminals when switching the unit on and off !

5.5.1 Operating

states

The Inverter has eight operating states. The explanations about each state are below.

Disconnected (default)

Before operation has commenced the inverter is in the disconnected state. In

this state, the inverter is totally isolated from the PV array and the utility grid.

Connecting to the PV array

When the inverter is in the "Disconnected" state, the ‘Inverter On’ button on

the GUI is selected and the PV voltage is kept above 400V for 5 seconds, the
system turns on the PV Array side contactor (PV_MC).

Connecting to Grid

When the inverter is in the “Connecting to PV Array” state and the PV voltage is

kept above the value of “MPPT V Start” parameter during the time set by “MPPT
T start” parameter, the contactor on the grid side is turned on. The inverter
keeps this state for 8 seconds.

Initializing MPP

The inverter calculates the MPPT start voltage which is product of measure-

ment of PV voltage and the parameter “MPP Factor”. After 5 seconds, the
inverter system enters into the "MPP start" state.

MPP start

In this state, the inverter controls the PV voltage. Reference of the PV voltage is

determined by MPPT start voltage which is calculated at “Initializing MPP”
state.

Table 3: Operating states