Preparing the Signaling Server for rack-mounting

Step

Action

The Front Mount Bracket assembly is not intended for use as a slide rail
system. The Signaling Server must be firmly attached to the rack.

1

Make sure the Signaling Server is not plugged into an electrical
outlet.

2

Align the end of the rail (A in

Figure 75 "Signaling Server brackets

(two of each)" (page 229)

) with the flange (B in

Figure 76 "Signaling

Server support bracket" (page 230)

) toward the back of the Signaling

Server. See

Figure 76 "Signaling Server support bracket" (page

230)

.

Figure 76
Signaling Server support bracket

3

Align the screw holes in the rack-mount rail with the mating holes in
the side of the Signaling Server. Use three screws (C) on each side.

Hand-tighten the screws to prevent cross-threading then use a
Phillips screwdriver to secure them.

4

Attach the bezel door to the faceplate of the Signaling Server, as
shown in

Figure 77 "Left hinge mount" (page 231)

and

Figure 78

"Right hinge mount" (page 231)

.

Nortel Communication Server 1000

Branch Office Installation and Commissioning

NN43001-314

01.02

Standard

Release 5.0

20 June 2007

Copyright © 2007, Nortel Networks

.

Advertising