MG 1000B platform hardware installation

a. Align the rack-mount brackets on the Signaling Server with the

slide rail system on the rack posts.

b. Slide the Signaling Server into place.

Refer to

Figure 81 "Rack-mounting the Signaling Server" (page 234)

.

Figure 81
Rack-mounting the Signaling Server

3

Tighten the screws through the faceplate of the Signaling Server to
the rack-mount bracket.

WARNING

Do not apply excessive torque while tightening the bolts.
The bezel door is plastic and does not require or withstand
overtightening.

—End—