Installation

System 2020 XT USB

3 - 42

ba76019e01

12/2012

3.9.2

Start checklist and system start

Before starting the system, carry out the system check using the
following checklist. Always carry out the check

 before the initial commissioning

 before any further commissioning if the system has been previously

extended or modified.

Starting the system

Switch on the voltage supply of the MIQ power supply module(s).

Start checklist

1 Is the sum of the power consumption of the components

smaller than the sum of the power delivery of all power supply
modules (see section 3.3)?

2 Are all IQ S

ENSOR

N

ET

components correctly connected with

one another (see section 3.5)?

3 Are all SN terminator switches correctly set (see section

3.9.1)?

4 Is the MIQ power supply module correctly connected to the

voltage supply?

5 Do the line voltage and line frequency agree with the data on

the name plate of the MIQ power supply module?

6 Are all IQ sensors ready for measuring, e.g. a D.O. sensor

filled with electrolyte solution?