Rockwell Automation 2500 CENTERLINE Motor Control Centers Installation Manual User Manual

Page 33

Advertising
background image

Rockwell Automation Publication 2500-IN001C-EN-P - April 2014

33

Install Columns

Chapter 3

Securing Double-front, One-column-wide Shipping Blocks

The following instructions are for bolting down the MCC. See

Figure 13 on

page 35

for weld down requirements.

1.

Remove the bottom wireway cover to locate the front mounting channel.
See

Figure 3 on page 15

for cover location.

2.

Secure the front of the MCC to the foundation according to the
dimensions below and the mounting channel requirements on

page 29

.

3.

Replace the bottom wireway cover.

4.

Repeat steps 1 through 3 for the other side of the double-front shipping
block.

IMPORTANT

Use steel M12 bolts (minimum Property Class 8.8) to secure columns to the
foundation. Not all bolt locations are used.

600…1000

460…860

70

6

234

542…942

1196

438…638

29

81

438…638

6

234

FRONT OF UNIT 2

FRONT OF UNIT 1

Protective Earth
(PE) Conductor

Protective Earth
(PE) Conductor

Dimensions are in mm.

Diagram shows top view of
600 mm column depths.

158

= Mounting hole
location not required.