Rockwell Automation Publication 2500-IN001C-EN-P - April 2014

67

Chapter

7

Commissioning

Introduction

This chapter provides guidance for the startup of a newly installed MCC.

We recommend that you make an itemized list that includes the following:

Serial number

Number of columns

Number of units and their corresponding voltage

Current ratings

Kilowatt ratings

Types of circuits

Fuse sizes

Circuit breaker ratings and trip settings

Other important data

This itemized list should be saved in a file along with other data for the MCC
such as, component manuals, MCC manuals, overload relay instructions and
wiring diagrams.

Pre-commissioning Checklist

ATTENTION: Follow applicable company safety procedures.

ATTENTION: To protect the safety of personnel performing the pre-energizing
check, verify remote MCC power sources are disconnected and locked in the
OFF/O position. Follow local codes and guidelines in addition to the
requirements of EN 50110.

Use a voltmeter to verify that the remote MCC power sources are disconnected.

ATTENTION: Power factor correction capacitors (PFCCs) must be applied
correctly. When PFCCs are connected to the motor circuit and the start-up
procedure requires the respective motors to be jogged, inched or bumped
(rotation direction check), temporarily disconnect PFCCs.

For additional assistance, contact your Rockwell Automation representative.