3 putting into operation – Metrohm 732 IC Detector User Manual

Page 55

Advertising
background image

3 Operating tutorial

732 IC Detector / 733 IC Separation Center

48

3.3

Putting into operation

After the complete IC system has been installed as described in sec-

tion 3.2, it can be put into operation. In what follows, all operating steps

up to the first calibration with the standard solution are described in se-

quence.
Please note that all displays refer to the condition in which the instru-

ment was put into operation for the first time (initial condition). If you do

not run through this tutorial until a later date, differences in regard to the

dialog language and the parameter values can appear. How you return

to the initial condition in such a case is described in section 5.4.9.
In this description of putting the instruments into operation, it is as-

sumed that all instruments are shut down and must first be switched

on. If this is not the case (e.g. if you start the operating tutorial immedi-

ately following the conditioning), you can skip steps 1

13

3.

1 Switch on external devices

Switch on recorder (if used).

Switch on «IC Metrodata for Win95» and PC

(if used).

Switch on other recording and evaluation system

(if used).

2 Switch on 709 IC Pump

Switch on 709 IC Pump with mains switch 29

29

(see section 2.6.4 of the 709 Instructions for Use).

3 Switch on remote control for 709 IC Pump

(the pump must be connected to the 732 IC Detector with a

6.2125.060 RS Cable for this)

Set sliding switch 36

36 at the rear of the 709 IC Pump to

"

RS

232

"

(see Fig. 2 of the 709 Instructions for Use).

Press key 88 <EXT.> on the 709 IC Pump to switch on the

external control (see section 3.6 of the 709 Instructions for

Use).
When the external control is activated, LED 77 above the

<EXT.> key lights up. All keys of the 709 IC Pump with the

exception of the <SELECT> key are blocked, operation is

now possible only via the 732 IC Detector.