Pre-power checks – Rockwell Automation 1395 Digital DC Drive FRN 5-10.10/9.30 User Manual

Page 247

Advertising
background image

Chapter 8
Start–Up

8-3

Figure 8.1
Bulletin 1395 Start-Up Sequence

External

Connection Checks

PRE-POWER CHECKS

Internal

Connection Checks

Feedback Board

Jumper Check

LIVE-POWER CHECKS

Incoming

Voltage Checks

Logic

Level Checks

Polarity

Checks

Monitor

Armature Voltage

PARAMETER PROGRAMMING

START-UP

With

Node Adapter

With

Discrete Adapter

TUNING

Pre-Power Checks

1. Verify all procedures listed in Chapter 6 Installation, have been

properly completed.

2. If you have not already done so, record the following information on

the Pre-Power Checklist Table on page 8-4.

Drive order number

Drive nameplate data

Motor nameplate data

Tachometer/Encoder data (if applicable)

Adapter boards used

External devices interfaced with Drive such as PLC, discrete I/O etc.