2 initial commissioning, 3 connecting the power pack, Initial commissioning – Xylem ProLab 4000 MULTIPARAMETER BENCHTOP METER User Manual

Page 24: Connecting the power pack

Advertising
background image

Commissioning

ProLab 4000

24

ba75646e02

01/2010

3.2

Initial commissioning

Perform the following activities:

z Insert the batteries (see page 187)

z Connect the power pack (see page 24).

z Switch on ProLab 4000 (see page 25).

z Connect the USB mouse (see page 26)

z Setting the language (see page 58)

z Set the date and time (see page 59)

z Set up the access authorization for user keys (see page 53)

z Connect the sensor (see page 27).

3.3

Connecting the power pack

The power pack supplies the meter with low voltage (9 V DC).

The batteries are only used to buffer the system time if the power sup-
ply is interrupted.

CAUTION

The line voltage at the operating site must lie within the input
voltage range of the original power pack (see page 195).

CAUTION

Use original power packs only (see page 195).

1

Insert the plug into the socket of the meter.

2

Connect the original power pack to an easily accessible power
outlet.
The self-test, meter designation, software version and subse-
quently the Standby display appear.

Advertising