14.1

95-8533

4-21

SYSTEM STARTUP

PRE-OPERATION CHECKS

General

Insulate all shields to prevent shorts to device housing

or to any other conductor.

Place alarm/release output in “Bypass/Isolate” when

servicing devices.

Maintain a log book containing the type and serial

numbers of devices as well as the location and date

of installation.

Maintain a log of maintenance activities.
Observe normal precautions for handling electrostatic

sensitive devices.

LON

Rocker switches for each LON device must be set to

the desired address prior to power-up.

Test the loop with no power applied. DC resistance

should be equal on A and B.

Check polarity on A and B (no rolls). COM 1 connects

to COM 2; COM 2 connects to COM 1. A connects

to A and B to B.

Measure voltage. A to chassis ground measures

approximately +7.5 vdc. B to ground measures

approximately –7.5 vdc.

Measure signal (400 mv P-P min.). (Use oscilloscope

if possible).

Check fault tolerance by introducing a short.

Controller

The I/O and LON wiring is correctly installed,

observing polarity. All cable shields are properly

terminated and insulated.

Power wiring is installed and power source is

operational.

Chassis ground stud must be connected to earth

ground.

Redundant Controller

The I/O and LON wiring is correctly installed,

observing polarity. All cable shields are properly

terminated and insulated.

Power wiring is installed and power source is

operational.

Chassis ground stud must be connected to earth

ground.

The HSSL cable is connected between the two

controllers.

EDIO/DCIO Module

Verify correct address setting.
Check signal circuits for correct polarity.
Check for correct installation of EOL resistors.

Relay Module

Verify correct address setting.
Check for correct output connections.

Analog Input Module

Verify correct address setting.
Check for correct input connections.
Check each channel with a loop current input.

Intelligent Protection Module

Verify correct address setting.
Check for correct input/output connections.

Power Supplies and Power Monitors

Verify all earth ground connections as specified in the

wiring instructions.

Verify correct ac power to supply.
Check power distribution to ensure that all devices

are receiving power.

Check power trouble indicator by introducing an open

to the battery.