Verifying Proper Power-Up of the CPU364 Ethernet Interface

After configuring the Ethernet Interface, follow the procedure below to verify that the Ethernet
Interface is operating correctly.

1.

Turn power OFF to the PLC for 3–5 seconds, then turn the power back ON. This will initiate
a series of diagnostic tests.

The EOK LED will blink indicating the progress of power-up.

2.

The Ethernet LEDs will have the following pattern upon successful power-up. At this time
the Ethernet Interface is fully operational and on-line.

LED

Ethernet Interface Online

EOK

(ON)

LAN

●/✲ (ON/Traffic)

STAT

(ON)

If the STAT LED is OFF, check the PLC Fault Table. Alternatively, use the Station
Manager LOG command as explained in GFK-1186, TCP/IP Ethernet Communications
for the Series 90 PLC Station Manager Manual

.

Problems During Power-up

If a problem is detected during power-up, the Ethernet Interface may not transition directly to the
Operational State. If the Interface does not transition to Operational, check the LED pattern on
the Interface and refer to the following chart and table for corrective actions.