7. Maintenance and Inspection

Periodical Inspection

Periodically inspect the inverter as described in the following table to prevent accidents
and to ensure high performance with high-reliability.

Part Replacement

Inverter’s maintenance periods are noted below. Keep them as reference.

Part Replacement Guidelines

Note:

Usage conditions are as follows:
• Ambient temperature: Yearly average of 30°C.
• Load factor: 80% max.
• Operating rate: 12 hours max. per day.

Location to Check

Check For

Solution

Terminal, unit mounting
screws, etc.

Connection hardware is properly
seated and securely tightened.

Properly seat and tighten hardware.

Cooling fins

Built up dust, dirt, and debris

Blow with dry compressed air:

39.2 X 10

4

to 58.8 X 10

4

Pa, 57 to 85 psi (4

to 6kg / cm

2

) pressure.

Printed circuit board

Accumulation of conductive
material or oil mist

Blow with dry compressed air:

39.2 X 10

4

to 58.8 X 10

4

Pa, 57 to 85 psi (4

to 6kg / cm

2

) pressure.

If dust or oil cannot be removed, replace the
inverter unit.

Power elements and
smoothing capacitor

Abnormal odor or discoloration

Replace the inverter unit.

Cooling fan

Abnormal noise or vibration.
Cumulative operation time
exceeding 20,000 hours.

Replace the cooling fan.

Part

Standard Replacement Period

Replacement Method

Cooling fan

2 to 3 years

Replace with new part.

Smoothing capacitor

5 years

Replace with new part.

(Determine need by inspection).

Breaker relays

Determine need by inspection.

Fuses

10 years

Replace with new part.

Aluminum capacitors on

PCBs

5 years

Replace with new board. (Determine need

by inspection).