3  Product Description

SMA Solar Technology AG

18

SCCP-JP-BA-A4-en-12

User Manual

3.2.4 Touch Display

Different kinds of Sunny Central data can be viewed on the touch display. You cannot use the touch display to set any

Sunny Central parameters, but only to configure display settings such as language, time and brightness.
The display screen is activated by touching the touch display. Tapping the symbols on the touch display activates the

corresponding functions. If the touch display has not been touched for five minutes, it will switch off.

3.2.5 Key Switch

The key switch is used to switch the Sunny Central on and off.

Switch Position "Start"

If the key switch is turned to Start, a motor drive switches the DC switchgear on and the Sunny Central switches from the

operating state "Stop" to the operating state "Grid monitoring". Providing there is sufficient irradiation and a valid utility

grid connection, the Sunny Central switches to feed-in operation. If there is insufficient irradiation and the input voltage is

therefore too low, the Sunny Central remains in the operating state "Grid monitoring".
With the order option "Q at Night", the inverter can support the utility grid with reactive power as required.

Switch Position "Stop"

If the key switch is turned to Stop while the Sunny Central is in the operating state "Grid monitoring", a motor drive

switches the DC switchgear off. The Sunny Central switches to the operating state "Stop".
If the key switch is turned to Stop while the Sunny Central is in the operating state "MPP load operation",

the Sunny Central switches to the operating state "Shutdown". Once the shutdown is complete, the AC contactor and the

DC switchgear are switched off automatically and the Sunny Central switches to the operating state "Stop".

MPP load operation

In MPP operation, the Sunny Central feeds power into the utility grid and operates

permanently at the maximum power point (MPP). Operation and the amount of

power being fed in appear on the touch display.
If the measured power P

PV

during the time interval PvPwrMinT is less than the

minimum feed-in power PvPwrMin or the key switch is set to Stop,

the Sunny Central switches to the operating state "Shutdown".
With the order option "Q at Night", the Sunny Central switches to the operating state

"Q at Night" if the measured power P

PV

during the time interval PvPwrMinT is less

than the minimum feed-in power PvPwrMin (see Section 3.8.8 "Q at Night",

page 31).

Shutdown

The Sunny Central is in the operating state "Shutdown". Operation appears on the

touch display.
If the key switch is set to Stop, the Sunny Central switches to the operating state

"Stop". The AC contactor and the DC switchgear open automatically.
If the Sunny Central shuts down because the feed-in conditions are no longer met,

the Sunny Central switches to the operating state "Grid monitoring".

Disturbance

If a disturbance occurs during operation, the Sunny Central switches off and displays

the word Fault and the actual disturbance in the touch display (see Section 10

"Troubleshooting", page 75).

Designation

Description

Advertising