7.6 Setting the Medium Voltage

The medium voltage of the Sunny Central must match the medium voltage of the medium-voltage grid.
It is important that the transmission ratio of the external MV transformer is adjusted at the same time. The undervoltage

side is already preset for the specific device.
Refer to the parameter list (see Section 12.1.2 "Grid Monitoring/Grid Limits", page 98) for the default value of the

parameter VRtg.

Procedure:

1. Log into the user interface.
2. Set the parameter TrfVolExlHi (see Section 6.2, page 40).
3. Set the parameter VRtg.
4. Confirm the parameter entry with [Save].

7.7 Activating the Manual Resume Mode

If the Sunny Central has switched off due to grid limit infringement, you can prevent an automatic restart of the

Sunny Central. The Sunny Central will not switch back on until the error has been acknowledged. You can activate the

Manual Resume Mode for individual errors of grid limit infringement. You can read off the reason for the current restart

block in the instantaneous value ManResStt.

Procedure:

1. Log into the user interface.
2. To activate the Manual Resume Mode for individual disturbances, set the desired parameters to On:

3. Confirm the parameter entry with [Save].

Manual Resume Mode after

Parameter

Disconnection due to overvoltage

ManResOvrVol

Disconnection due to undervoltage

ManResUndrVol

Disconnection due to overfrequency

ManResOvrFrq

Disconnection due to underfrequency

ManResUndrFrq

Disconnection due to passive islanding detection ManResPID
Disconnection due to disturbance in a line

conductor

ManResPLD