Seal the shaft with a packed stuffing box – Goulds Pumps 3196 i-FRAME - IOM User Manual

Page 117

Advertising
background image

Maintenance

9. Install a dynamic-seal assembly and nuts (370H).

10. Check the stuffing-box-cover runout and rotate the indicator through 360 degrees.

An indicator reading that is greater than 0.005 in. (0.013 mm) indicates a problem.

Seal the shaft with a packed stuffing box

WARNING:
Packed stuffing boxes are not allowed in an ATEX-classified environment.

Pumps are shipped without the packing, lantern ring, or split gland installed. These parts are
included with the box of fittings shipped with each pump and must be installed before startup.
1. Carefully clean the stuffing-box bore.
2. Twist the packing enough to get it around the shaft.

Model 3196 i-FRAME Installation, Operation, and Maintenance Manual

115

Advertising