Placement of system components

• Place all system components in position prior to making electrical, gas and interface connections. Use the

diagram on the following page for component placement guidelines.

• Ground all system components to earth. See

Grounding requirements in this section for details.

• To prevent leaks in the system, tighten all gas and water connections as shown below:

Torque specifications

Gas or water

hose size

lbf-in

lbf-ft

kgf-cm

Up to 10 mm (3/8")

75-85

6.25-7

8.6-9.8

12 mm (1/2")

360-480

30-40

41.5-55