Dlx and remote system end-to-end test procedures – ADC Soneplex Broadband System User Manual

Page 46

Advertising
background image

ADCP-61-471 • Issue 4 • June 2000 • Section 2: Operation and Maintenance

2-23

© 2000, ADC Telecommunications, Inc.

NTP-010

Page 1 of 2

DLX AND REMOTE SYSTEM END-TO-END TEST PROCEDURES

Summary:

This procedure provides instructions for performing end-to-end tests between the

DLX modules and the remote system. Performing an end-to-end test includes connecting the
cross-connect jumper wires, and then sending a test signal between the chassis and the network
equipment. This procedure assumes that the T1 facility between the Soneplex Broadband chassis
and network equipment (e.g., DLC, channel bank, etc.) is functional, and that the DLX modules
to be tested have already been installed. This procedure must be performed before attempting to
operate the entire circuit or system that will be using this equipment.

Warning:

To prevent electrical shock, never install telephone equipment in a wet

location or during a lightning storm. When installing or modifying telephone lines,
disconnect lines on the network side before working with uninsulated lines or terminals

.

Caution:

Electronic modules can be damaged by electrostatic discharge (ESD). Before

handling modules, wear an anti-static discharge wrist strap to prevent damage to
electronic components. Place modules in anti-static packing material when transporting
or storing. When working on modules, always place them on an approved anti-static mat
that is electrically grounded.

Do Items Below in The Order Listed

For Details Go To

1. Obtain the following tools and equipment:

Anti-static wrist strap

DS3 test set with DS1 option (for central office end of the
circuit)

DS1 test set (for remote end of the circuit)

VT-100 compatible terminal or computer with terminal
emulation software

2. Coordinate test with a technician located at the remote end of the

circuit and ensure test procedures there have been completed.

3. Open the chassis front cover.

4. Momentarily press the LMPTST switch on the APU front panel

and verify that all indicators light.

5. Connect terminal equipment to Craft port on the front of the MPU.

DLP-504

6. Log on to the system.

DLP-526