ADCP-61-471 • Issue 4 • June 2000 • Section 2: Operation and Maintenance
2-24
© 2000, ADC Telecommunications, Inc.
NTP-010
Page 2 of 2
Do Items Below in The Order Listed
For Details Go To
8. Enter Target Identifier and set date and time now or during
provisioning (the turn-up process).
9. Configure DS3 MUX as required.
10. Configure DLX modules as required.
11. Connect the test equipment at both ends of the system and perform
12. If the DS3 MUX protect module is installed:
• Execute Force/APS commands through the Craft Interface.
•
Perform Manual (Force) Switch to Protect test on DS3 MUX
module.
• Perform APS test on DS3 MUX module.
13. Make any necessary cross-connects at the DSX.
14. Log off from the Craft Interface system.
15. Complete assignment forms and update office records as required