Voltage relay, Rela y check out – Xylem GSSERVICE R2 Service Manual Submersible Pumps & Jet Pumps User Manual
Page 17
Advertising
![background image](/manuals/310401/17/background.png)
15
Step 2, Contact Test
1. Meter setting: R x 1.
2. Connections: #1 & #2.
3. Correct meter reading:
Zero for all models.
B. F.E. Blue Relay - Solid State
1
⁄
3
– 1 HP QD Control Boxes
Used from 1994 until present time:
Step 1, Triac Test
1. Meter setting: R x 1,000.
2. Connections: Cap and B terminal.
3. Correct meter reading: Infinity for all
models.
Step 2, Coil Test
1. Meter setting: R x 1.
2. Connections: L1 and B.
3. Correct meter reading:
Zero ohms for all models.
RELA
Y
CHECK
OUT
Voltage Relay
CONtrOl bOxeS (CeNtriPrO Or F.e.)
Advertising