10.Though a prompt asks you to test distress alert, do not press any

key. The alert test is automatically conducted two minutes later.

11. When testing is completed the indication TESTING is replaced

by IDLE.

12.The test results appear on the PV Test Result screen. (The next

section shows how to interpret the results.)

Results of PV test

1. At the standby display, press [F7] to display the Options menu.

2. Press [6] to display the Test menu.

Figure 8-5 Test menu

3. Press [2] to display the results of the PV test.

Figure 8-6 Sample PV test results

Note:

If the communication unit is off or malfunctioning, “DCE

error: No response from DCE!!” appears. Check the con-
nection between the communication unit and the terminal
unit.

4. To escape, press any key. The standby display appears.

Interpreting the PV tests results display

Test Date & Time:

Date and time of test

Attempts:

Number of times the PV test was con-
ducted.