NOTE: Ensure the boom is not fully retracted for following

steps.

6.

Using tool P/N 4120043, torque outer mid extend
adjuster nuts to 80 ft.lb. (112 Nm), alternating
between the two ropes until both maintain the
required torque.

7.

Using tool P/N 4120040, torque fly extend adjuster
nuts to 10 ft.lb. (14 Nm), alternating between the four
ropes until all maintain the required torque.

BASE BOOM

INNER MID BOOM

NOTE: Boom shown in fully retracted position.

OUTER MID BOOM

FLY BOOM

9.5 ± 0.5”

241 ± 13 mm

3.5 ± 0.5”

90.5 ± 13 mm

8.0 ± 0.5”

203 ± 13 mm

Figure 4-28. Wire Rope Tensioning Figure A