Installing counterbalance valve, Installing counterbalance valve -21, Rotator counterbalance valve -21 – JLG 510AJ Service Manual User Manual

Page 219

Advertising
background image

SECTION 4 - BOOM AND PLATFORM

3121181

– JLG Lift –

4-21

Installing Counterbalance Valve

Refer to Figure 4-8., Rotator Counterbalance Valve.

1.

Make sure actuator surface is clean and free of any con-
tamination and foreign debris - including old Loctite.

2.

Make sure new valve has O-rings in counter-bores of
valve to seal it to the actuator housing.

3.

Bolts that come with the valve are grade 8 bolts. New
bolts should be installed with a new valve. Apply Loctite
#242 to shank of three bolts at time of installation.

4.

Torque 1/4" bolts 110 - 120 in-lb (12.4 to 13.5 Nm). Do
not torque over 125 in-lb (14.1 Nm). Torque 5/16" bolts
140 in-lb (15.8 Nm). Do not torque over 145 in-lb (16.3
Nm).

Figure 4-8. Rotator Counterbalance Valve