TroubleshooTing and sysTem TesTs

powermax

65/85

Service Manual

5-13

IGBT test preparation

Before testing with the Hypertherm IGBT tester, connect the colored leads to the IGBT as shown on the next page.

Note: Before an IGBT can be tested, it must be electrically isolated from all circuits. If the IGBT is installed in a power

supply, remove the power board and any lead connections before testing.

The illustrations below depict three common configurations of an IGBT. Each connection on the IGBT will be labeled

with an abbreviation. They may be labeled as C, E, G or 1, 2, 3 with a schematic that shows numbers and pin functions.

Yellow lead

Gate 2 (G2)

Black lead

Emitter 2 (E2)

Red lead

Collector 2, (C2)

IGBT, Inverter

Test 1

Yellow lead

Gate (G)

Black lead

Emitter (E)

Red lead

Collector (C)

IGBT, PFC

Yellow lead

Gate (G)

Red lead

Collector (C)

Black lead

Emitter (E)

IGBT, Pilot arc

IGBT, Inverter

Test 2

Yellow lead

Gate 1 (G1)

Red lead

Collector 1, (C1)

Black lead

Emitter 1 (E1)

Caution: Failure to isolate the IGBT may result in false readings and/or damage to the

IGBT tester.