Venting & air — general, Gv90, Boiler manual – Weil-McLain GV90+ User Manual

Page 29

Advertising
background image

Part number 550-142-054/0411

29

GV90+

gas

-

fired

water

boiler

— Boiler Manual

Venting & air — general

GV90+ boilers must be vented and

supplied with combustion and venti-

lation air using piping and methods

described in this manual

.

Every boiler must have its own vent

.

DO NOT

common vent with any other

appliance.

Inspect finished vent and air piping

thoroughly to ensure all are airtight

and comply with the instructions

provided and with all requirements of

applicable codes.

Failure to provide a properly-installed

vent and air system will cause severe

personal injury or death.

If the vent/air piping configurations

covered in the GV90+ boiler manual

cannot be applied for a particular

installation, contact Weil-McLain for

assistance. Other configurations may

be available.

Where vent piping is routed through

an unheated space

, apply minimum

1 inch of foil-faced fiberglass insulation

on the length of the vent pipe in the

unheated space.

Installations must comply with local

requirements and with the National

Fuel Gas Code, ANSI Z223.1 for U.S.

installations or CSA B149.1 or B149.2

for Canadian installations.

Use only the materials listed in this

manual for vent and air pipe and fit-

tings. See Figure 40, page 33.

If used, a masonry chimney can

ONLY be used as a PIPE CHASE for

vent and air pipes

— The vent and air

piping must be installed as instructed

in this manual and all joints must be

sealed. The chimney must be used

only for GV90+ boilers. NO OTHER

appliance or fireplace can be connected

to the chimney. The chimney must be

straight, with no offsets, and the vent

and air piping materials must comply

with this instruction manual. The

chimney must be fitted with a sealed

access opening, through which the in-

terior of the chimney can be inspected.

The chimney (and liner, if installed)

must be inspected at least once annu-

ally to verify condition.

Failure to comply could result in severe

personal injury, death or substantial

property damage.

When removing a boiler from an existing

common vent system

The GV90+ boiler cannot be common vented with any other
appliance.

When an existing boiler is replaced with a GV90+ boiler,

the GV90+ boiler CANNOT use the existing common vent. The GV90+
boiler requires its own vent and air piping, as specified in this manual. This
may cause a problem for the appliances that remain on the old common
vent, because the vent may be too large. The following test, required by
ANSI Z21.13, is intended to check for proper operation of the appliances
remaining on the old common vent system.

Vent system verification

At the time of removal of an existing boiler, the following steps shall be
followed with each appliance remaining connected to the common venting
system placed in operation, while the other appliances remaining connected
to the common venting system are not in operation. Seal any unused open-
ings in the common venting system.

Existing vent test procedure

(The following is intended to test whether the appliances
remaining on an existing vent system will operate
satisfactorily.)

1. Visually inspect the venting system for proper size and horizontal pitch

and determine there is no blockage or restriction, leakage, corrosion or
other deficiencies which could cause an unsafe condition.

2. Test vent system — Insofar as is practical, close all building doors and

windows and all doors between the space in which the appliances
remaining connected to the common venting system are located and
other spaces of the building. Turn on clothes dryers and any appliance
not connected to the common venting system. Turn on any exhaust
fans, such as range hoods and bathroom exhausts, so they will oper-
ate at maximum speed. Do not operate a summer exhaust fan. Close
fireplace dampers.

3. Place in operation the appliance being inspected. Follow the lighting in-

structions. Adjust thermostat so appliance will operate continuously.

4. Test for spillage at draft hood relief opening after 5 minutes of main

burner operation. Use the flame of a match or candle, or smoke from
a cigarette, cigar, or pipe.

5. After it has been determined that each appliance remaining connected

to the common venting system properly vents when tested as outlined
herein, return doors, windows, exhaust fans, fireplace dampers, and any
other gas-burning appliance to their previous conditions of use.

Any improper operation of common venting system should be corrected
so the installation conforms with the National Fuel Gas Code, ANSI Z223.1
— latest edition. Correct by re-sizing to approach the minimum size as
determined using the appropriate tables in Part 11 of that code. Canadian
installations must comply with B149.1 or B149.2 Installation Code.

Advertising