Direct exhaust — vertical, Gv90, Boiler manual – Weil-McLain GV90+ User Manual

Page 53

Advertising
background image

Part number 550-142-054/0411

53

GV90+

gas

-

fired

water

boiler

— Boiler Manual

DIRECT EXHAUST — Vertical

Allowable vent/air pipe materials &

lengths

Use only the vent materials and kits listed

in Figure 40, page 33. Provide pipe adapt-

ers if specified.

1. Locate the termination such that the total air piping

and vent piping from the boiler to the termina-

tion will not exceed the maximum length given in

Figure 39, page 32.

Determine termination location

1. The vent terminations must be installed as shown

in Figure 63, page 53.

2. The terminations must comply with clearances and

limitations shown in Figure 41, page 35.

3. Locate the termination so it is not likely to be dam-

aged by foreign objects, such as stones or balls, or

subject to buildup of leaves or sediment.

Multiple vent/air terminations

1. Terminate each vent of multiple direct exhaust

GV90+ boilers as described in this manual for

individual vents.

2. Space terminations as required for best installation

practices and required maintenance.

Prepare roof penetration

1. Vent pipe penetration:

a. Cut a hole for the vent pipe. For either com-

bustible or noncombustible construction, size

the vent pipe hole at least 0.5” larger than the

vent pipe diameter.

b. Hole diameter in the metal plates must be at

least 4” for PVC pipe. For AL29-4C vent pipe

and coupling (or elbow) — size hole 0.5” larger

than vent pipe outside diameter.

c. Insert a galvanized metal thimble in the vent

pipe hole.

2. Follow all local codes for isolation of vent pipe when

passing through floors, ceilings and roofs.

3. Provide flashing and sealing boots sized for the vent

pipe and air pipe.

Where the vent penetrates the roof, the an-

nular space around the penetration must

be permanently sealed using approved

materials to prevent entry of combustion

products into the building.

Figure 63

INSTALLATION SEQUENCE — Direct exhaust vertical

Step 1

Read and follow all instructions in this manual.

DO NOT

proceed with vent/air installation until you have read

page 29 through page 35, page 49 and page 50.

Step 2

Install the boiler in a location that allows proper routing of

all vent and air piping to the selected sidewall location.

Step 3

Make sure the selected vertical termination location com-

plies with Figure 41, page 35.

Step 4

Use only the vent materials listed in Figure 40, page 33.

Provide pipe adapters where required. Vent piping and air

piping lengths must not exceed the values shown in Fig-

ure 39, page 32.

Step 5

Prepare the vertical penetration and secure penetration

components as instructed in this section. See “Prepare roof

penetrations” on page 43 and “Termination and fittings” on

page 44.

Step 6

The vent piping must terminate in a

coupling pointed

upward

as shown above.

Step 7

Install vent and air piping between the boiler and the verti-

cal termination. Slope horizontal piping downward toward

the boiler at least 1/4 inch per foot. Install pipe supports

every 5 feet on both the horizontal and vertical runs. Install

a hanger support within 6 inches of any upturn in the pip-

ing. See page 48 for general guidelines.

Step 8

Maintain minimum clearance of C\zn inch between vent pipe

and any combustible wall or material.

Step 9

Insert the vent piping through the vertical penetration and

secure the termination coupling.

Step 10

Maintain clearances shown above. Vent terminations must

be fitted with a bird screen as shown.