Sidewall with W-M vent/air plate

Allowable vent/air pipe materials &

lengths

Use only the vent materials and kits listed

in Figure 40, page 33. Provide pipe adapt-

ers if specified.

1. Locate the termination such that the total air piping

and vent piping from the boiler to the termina-

tion will not exceed the maximum length given in

Figure 39, page 32.

Determine termination location

1. The vent/air cap must be installed as shown in

Figure 46, page 38.

2. The termination must comply with clearances and

limitations shown in Figure 41, page 35.

3. Locate the termination so it is not likely to be dam-

aged by foreign objects, such as stones or balls, or

subject to buildup of leaves or sediment.

Multiple vent/air terminations

1. When terminating multiple GV90+ boilers, ter-

minate each vent/air connection as described in

this manual.

All vent pipes and air inlets must ter-

minate at the same height to avoid pos-

sibility of severe personal injury, death or

substantial property damage.

2. Place wall penetrations to obtain minimum clear-

ance as shown in Figure 44 for U. S. installations.

For Canadian installations, provide clearances re-

quired by CSA B149.1 or B149.2 Installation Code.

3. The air inlet of a GV90+ boiler is part of a direct

vent connection. It is not classified as a forced air

intake with regard to spacing from adjacent boiler

vents.

4. Combustion air (NOT vent piping) can be mani-

folded as shown in Figure 37, page 31.

Figure 43

INSTALLATION — W-M sidewall vent/air plate

Step 1

Read and follow all instructions in this manual.

DO NOT

proceed with vent/air installation until you have read

page 29 through page 35.

Step 2

Install the boiler in a location that allows proper routing of

all vent and air piping to the selected sidewall location.

Step 3

Make sure the selected sidewall termination location com-

plies with Figure 41, page 35. (Multiple boiler sidewall plates

must also comply with Figure 44, page 38.)

Step 4

Use only the vent materials listed in Figure 40, page 33.

Provide pipe adapters where required.

Step 5

Vent piping and air piping lengths must not exceed the

values shown in Figure 39, page 32.

Step 6

Prepare the sidewall penetrations and secure the sidewall

plates as instructed in this section. See “Install Weil-McLain

vent/air cap” on page 38.

Step 7

The Weil-McLain plate termination must be installed before

piping from the boiler to the termination.

Step 8

Install vent and air piping between the boiler and the vent/

air termination plate. Slope horizontal piping downward

toward the boiler at least 1/4 inch per foot. See page 48 for

general guidelines.

Step 9

Install pipe supports every 5 feet on both the horizontal and

vertical runs.

Step 10

Install a hanger support within 6 inches of any upturn in

the piping.

The Weil-McLain vent/air termination

cap can be used to terminate the vent

pipe for multiple boiler applications

using the manifolded combustion

air option. The vents must be lo-

cated following the restrictions in Fig-

ure 41, page 35

and Figure 38, page 31.