Installation Guide

H5692448

CC848815325 r06 May 2013

35

Step

Action

1

Verify that the measured voltage matches

the bus label using a meter.

Figure 53 Battery Bus Labels

Connect Load Wiring

Figure 54 Distribution Assignment Record Label

WARNING: Shock Hazard and Equipment Damage

Do not install circuit breakers or load fuses until the load equipment is ready to be

energized.

When a load is ready to be energized

1. Connect the load to the distribution panel.
2. Install the circuit breaker of fuse.

CAUTION: Equipment Damage

Ensure Circuit Breakers are in the OFF position prior to installation.

Ensure Fuse Holders are empty prior to installation.


Notes:

1. Start from the top most position and work down the panel. This will allow orderly and managed cable

dressing as loads are added in this installation and in the future.

2. Connect the Load Return cable before the Load cable for each load.

The Load Return connection is blocked by the Load cable, if installed.

3. Follow steps of each section below as appropriate to breakers and fuses to be installed.
4. Repeat steps of each section as appropriate.
5. Bolt-in breakers may be factory installed.

-48V Battery Bus

+24V Battery Bus

Blue

Orange

Note that a space to record the

distribution assignments is available on

the inside of cabinet door:

Distribution

Identification