Page 47: Figure 67 controller connections

Advertising
background image

NE-M

Installation Guide

H5692448

CC848815325 r06 May 2013

47

Figure 66 Millennium II Circuit Card - Field

BSL Alarm Termination Board

An insulation displacement (punch down) type alarm terminal board (BSL3, 848741711) is provided with the system.

For a wire wrap type terminal board, order BSL4 (848749507) and perform the following steps:

Step

Action – Millennium II

1

In the upper right hand corner of the MCR1 board, find the alarm board already installed.

2

Remove the two screws holding the board at the top.

3

Holding the board on both sides, slowly, but firmly, remove the alarm board from the P8 connector.

4

Connect the new alarm board to P8 and press down firmly, until the board is seated.

5

Secure the alarm board at the top using the two screws removed earlier.

Connect Controller Wiring – Millennium II

All connections to the controller are made through appropriate cable assemblies. The controller has been designed

to separate outputs, inputs, communication, and plant specific items onto to individual connectors.

Figure 67 Controller Connections

RPM Modules

MCR1 Card

Panel