Operator’s manual – Great Plains DICKEY-john IntelliAg Planter-Drill Control L3 User Manual

Page 66

Advertising
background image

OPERATOR’S MANUAL

IntelliAg PDC User 2 & 3

11001-1501-200811

58 / SYSTEM CONFIGURATION

The precharge feature is typically used in applications that have significant
distance between the implement row unit and storage bulk tank where seed
placement takes several seconds due to the travel time of the seed/fertilizer
from the bulk tank to the ground.

The precharge feature will operate until the precharge time lapses or the
precharge ground speed has been exceeded. If the master switch is turned
OFF, the precharge feature will abort.

A Precharge Alarm will display any time the preset feature is established or
changed and the master switch is turned ON.

IMPORTANT: A Precharge number MUST be entered as a positive

number (5.0 seconds) for the system to identify between
a Precharge or Delay Time state.

To activate Precharge:

1. At the Control Channel screen, enter a Precharge time. A Precharge

Time must be entered as a POSITIVE number (5.0 seconds) before
the Precharge Ground Speed feature displays on the Ground Speed
Setup screen (Refer to Ground Speed Setup section).

2. Press the Work Screen button and select the Speed Set button.
3. Enter a Precharge Ground Speed greater than 0.

IMPORTANT: Turn the master switch ON to activate the Precharge

feature.

Delay Time

IMPORTANT: A Delay Time number MUST be entered as a negative

number (-5.0 seconds) for the system to identify
between a Delay Time or Precharge state.

NOTE: Delay Time functionality may

work differently than described
above if the system has been
purchased direct from the
original equipment
manufacturer. Refer to the
manufacturer’s operator
manual for further instruction.

With an Implement Lift Switch

Delay Time determines the length of time before the control channel will
start after the master switch has been turned ON and the implement switch
is in a lowered position.

• The system will immediately shutdown the channel when the

implement lift switch is in the raised position.

• The system will delay the channel shutdown if the master switch is

turned OFF and the implement is in the down position.

Advertising
This manual is related to the following products: