22. The Select Stencils dialog box opens. Add, remove, or re-order stencils. Click Finish

23. The Synchronization Status dialog box opens as the synchronization process begins. It then

displays the progress of the synchronization. Once “Synchronization Complete” opens, click OK
to open your IzoT Commissioning Tool network.

24. Verify that your OpenLNS CT drawing accurately represents the network. Ensure that all devices

on the physical network and all the connections between the devices appear on the drawing. You
can refer to the trace log created during the synchronization process. The trace log file is located
in C:\Users\Public\Documents\LonWorks\OpenLnsCt\Databases\<network> or in the network
database path you specified in the naming window of the Network Wizard. Make changes to your
IzoT Commissioning Tool network, if necessary, until it matches the physical network.