Refreshing the izot commissioning tool network, Merging izot commissioning tool networks, Merging networks – Echelon IzoT Commissioning Tool User Manual

Page 265

Advertising
background image

The resync log is stored in the drawing directory of the current IzoT Commissioning Tool network
design.

17. If the OpenLNS CT drawing is being synchronized to match the network database and the

Automatically Drop Device, FB, and Subsystem Shapes check box was cleared, the Missing
Shape
dialog opens for each object in the network database that is not represented in the
OpenLNS CT drawing.

a. Click OK. The Missing Shape dialog closes and you are returned to the OpenLNS CT

drawing.

b. Drag a single SmartShape from an IzoT Commissioning Tool stencil to the OpenLNS CT

drawing to represent the missing SmartShape. IzoT Commissioning Tool assigns the
SmartShape to the specified object in the OpenLNS network database.

c. Click Add-ins, point to Synchronization, and then click Resynchronize to re-open the

Missing Shape dialog and assign the next missing SmartShape.

d. Repeat steps a – c for each missing SmartShape. Once all missing SmartShapes have been

added and the connections have been updated, resynchronization will be complete.

Tips:

• The first time you resynchronize an OpenLNS CT drawing created with a previous version of IzoT

Commissioning Tool, most connections that span multiple documents will automatically be
deleted and then re-created. This speeds up any subsequent resynchronizations.

• The first time you resynchronize an OpenLNS CT drawing created with an older version of Visio,

select the Reset Visio Workspaces option in the Synchronize OpenLNS CT Drawing dialog.
This automatically saves the documents in your drawing to the Visio 2010 or Visio 2003 format.
Otherwise, IzoT Commissioning Tool prompts you whether to save the documents in your
drawing in Visio 2002 format or the current Visio format. If you answer Visio 2002, IzoT
Commissioning Tool will continue to prompt you every time you resynchronize the drawing.

• If you have stencils from an older version of Visio that you want to use, open and save the stencils

individually in Visio 2010 or Visio 2003. Otherwise, Visio will prompt you each time the
drawing is closed as to whether to save the changes to the stencil, but it won’t save any changes
because it opens these stencils as read-only.

Refreshing the IzoT Commissioning Tool Network

IzoT Commissioning Tool caches data from the OpenLNS network database to improve performance.
If another OpenLNS application or plug-in updates data that has been cached by IzoT Commissioning
Tool and does not generate an appropriate OpenLNS event, the IzoT Commissioning Tool cache may
lose synchronization with the OpenLNS network database. You can force IzoT Commissioning Tool
to process and release the cache by clicking Add-ins, pointing to Synchronization, and then clicking
Refresh.

Merging IzoT Commissioning Tool Networks

You can initially install a large L

ON

W

ORKS

network as a number of smaller independent networks—

each with their own network database—and then later merge the networks into one network.
Examples of installations that may use this technique include the following scenarios:

Multiple systems. When multiple systems are being installed, the installers for each system want

to install and debug their installation without interference from other systems. When each system
has been correctly installed, they can be merged into a single network.

Incomplete infrastructure. Portions of a building, such as the floors of a high-rise, may need to

be installed before connectivity exists for the entire site (before there is a backbone channel
connecting the floors together, for instance). You can install each floor of the network as part of a

IzoT Commissioning Tool User’s Guide