OpenLNS CT Drawing

Synchronize Drawing
to Database (fix-up
Drawing)

Updates the OpenLNS CT drawing to be consistent with the
OpenLNS database.

Synchronize Monitor
Sets between
Drawing and
Database

Updates the monitor sets in the OpenLNS CT drawing to be
consistent with the OpenLNS database. A monitor set is a group of
point definitions that IzoT Commissioning Tool uses to monitor and
control network variables. If the type or format of a monitored point
has changed, the value displayed will be updated when the point is
monitored with IzoT Commissioning Tool.

Update Shapes to
Current IzoT
Commissioning Tool
Version

Updates SmartShapes to the current version of IzoT Commissioning
Tool if the OpenLNS CT drawing was originally created with an
earlier version of IzoT Commissioning Tool.

Update Shapes to
Current IzoT
Commissioning Tool
Language

Updates SmartShape menus to current IzoT Commissioning Tool
language. For example, if you open a network with the German
version of IzoT Commissioning Tool that was created with the
English version, this option will convert the SmartShape menus to
German. All the dialogs are in the language of the respective
version of IzoT Commissioning Tool. The language conversion may
take some time; therefore, this option should not be used frequently.

Reset Visio
Workspaces

Corrects instances in which Visio has added multiple documents and
stencils to the drawing in an IzoT Commissioning Tool network.
For each drawing in the network, IzoT Commissioning Tool opens
the drawing file, closes all other open drawings, opens the standard
set of stencils, and saves the drawing as a workspace.

This option also automatically upgrades the drawings in the IzoT
Commissioning Tool network to the current version of Visio.

4. If you are only validating or repairing the OpenLNS network database, click Finish to begin the

resynchronization process and skip to step 16 in which the Synchronization Status dialog opens.
Otherwise, click Next. The Synchronization Scope dialog box opens.

IzoT Commissioning Tool User’s Guide