Chapter 7: Maintenance & Inspection

7.1.2 Press Fixture

Recommended Schedule: Daily

• Ensure all light curtains and safety devices are operating properly - immediately shut

down press if any problem is found and do not operate until safety devices are in
proper working order.

• Ensure any fixture is securely attached to the press ram (and/or press base) and all

fasteners are tight.

7.1.3 Homerun Cables

Recommended Schedule: Quarterly

These cables connect the tool to the SAN unit. Ensure the following conditions are met:

• The cables are free from unnecessary force and tension.
• The cables are secured away from any movement.
• The cables are in good condition, sufficiently insulated with no indication of broken wires.
• The cables are free from excessive contamination and foreign matter.
• The cables are securely connected to the SAN unit and to the press.
• The cables are free from heat distortion, and are not warm or hot to the touch.

The cables, cable connectors, and connector screws are securely and correctly fastened.

7.1.4 SAN Unit

Recommended Schedule: Quarterly


The SAN Unit requires careful use and handling. Inspect each SAN unit and ensure the
following requirements are met:

• The environmental conditions are within specifications.
• There is no moisture, oil, or foreign matter on the unit.
• The unit is securely mounted, with appropriate clearance on all sides.
• All screws (for the cover of the unit and for mounting) are correctly tightened.
• The input power remains within specifications at all times.
• The unit is not producing any abnormal (excessive) heat.
• Unit cables (on the front and the underside) are securely fastened and without damage.

7.1.5 Air Handling Unit

Recommended Schedule: Every 2 months (sooner if external environment is harsh i.e.
machining area with coolant mist in air)


Equipment supporting the

enFORCE

System's environment must be sufficiently maintained.

Internal electrical enclosure (which the SAN units are housed) heat load can be calculated using
the internal power consumption data in table 2.3. Verify support equipment meets the following
requirements, as applicable to the unit type:

• The unit is free from dust, oil, and foreign matter.
• All filtration devices are clean, and air flow is not impeded.
• The unit is securely and correctly mounted.
• The input power remains within specifications at all times.
• All fans are functioning properly with no abnormal sound or vibration.