11.

Inspection and Maintenance

11.3 Replacing Flow meter in ZR40H Autocalibration Unit

(1) Remove piping and wiring, and remove the ZR40H from the 2B pipe or wall

mounting.

(2) Remove four M6 bolts between brackets.
(3) Remove piping extension
(4) Remove bolts holding flow meter, and replace it. A white back plate (to make the

float easy to see) is attached. The end of the pin holding down the back plate must
be on the bracket side.

(5) Replace piping, and fix M6 bolts between brackets. *1

*1 : When disassembling and reassembling, mark original positions, and tighten an

extra 5-10

Њ when reassembling. After tightening, do a liquid leakage test.

COM ON S N

Z RO

F11.9E.eps

Bolt fixes bracket

Flow meter with back plate

Connecter

Fig. 11.9

Flow meter replacement