SERVOPACKs and Converters

Inspect and check the following items, and take appropriate measures before per-
forming trial operation if any problem exists.

• Are all installation, wiring and connections correct?
• Is the correct power supply voltage being supplied to the SERVOPACK and the

converter?

„

Installing the Servomotor, SERVOPACK, and Converter

Install the servomotor, the SERVOPACK, and the converter according to the installa-
tion conditions.

<Note>

• Be sure to secure the servomotor to the equipment, or the servomotor may turn

over when it starts rotating.

• Do not connect anything to the servomotor shaft.

Secure the servomotor to the machine.

Do not connect any load to the shaft.