Initial Start-up

The system is ready to be powered up. Please verify all connections are as described prior to
applying ac power.

Step Action

1.

If using battery disconnect switches place them in their ON/CLOSED
positions prior to applying ac power.

2.

Turn on the ac service circuit breakers to apply power to the CPS6000 power
system.

3.

Verify that All LEDs on all components including rectifiers, controllers, LVD
boards, and remote voltage monitor modules are green.

4.

Verify that the reading on the controller display is 54.5 Vdc. Note that if the
connected batteries are not fully charged, the voltage may be lower. If
possible, open the external disconnect switches or activate the disconnect
switches in the Distribution Module prior to making measurements.

5.

If the conditions in Steps 3 and 4 are not met refer to Section 13,
Troubleshooting.

6.

Refer to Section 6 for changing system parameters from the default settings if
required (float voltages, alarm thresholds, controller settings, etc.)

7.

For QS841A only :
If network parameters have been obtained from the corporate network
administrator and the controller is ready to be configured for network
operations follow the steps below: Otherwise the installation is complete.

The following Network Configuration Parameters must be obtained
from your Network Administrator before starting:
• IP address
• Subnet mask
• Host name
• Gateway IP address

Note: Host and Gateway may be optional.

Configuration of the network parameters may be done in one of two different
ways:

(1) Easy View
(2) Serial Port

8

Configuring the network parameters for QS841A only :

Using EasyView

Using a PC with EasyView running connected to J3 of the QS841A go to
Configure

Æ

Port Communications

Æ

Network Port 1. Enter all network

parameters and click “OK” to save.