Readiness checklist – Nortel Networks 1000E User Manual

Page 175

Advertising
background image

Installing a Signaling Server

Page 175 of 466

Communication Server 1000E

Installation and Commissioning

rack mounting, as opposed to two-post rack mounting for the Nortel ISP1100
server.

Readiness checklist

Before installing a Signaling Server in a CS 1000 system, complete the
following checklist.

IMPORTANT!

Instructions to install an IBM X306m or HP DL320-G4 COTS 1U server
are not included in this chapter. Detailed installation instructions can be
found in the IBM xSeries 306m Types 8848 and 8491 User Guide or the
HP ProLiant DL320 Generation 4 Server User Guide shipped with the
server.

WARNING

Do not modify or use a supplied AC-power
cord if it is not the exact type required in the
region where the Signaling Server is installed
and used. Be sure to replace the cord with
the correct type.