Installing system grounds

Page 93 of 466

Communication Server 1000E

Installation and Commissioning

Follow Procedure 3 to install a ground bar.

Procedure 3
Installing an NTBK80 Ground Bar

1

Place the ground bar near the equipment.

Note: The ground bar is a bridging point for ground wires from up to
six components.

2

Connect the ground bar to the ground bus in the AC electrical panel using
#6 AWG wire. See Table 12 on

page 93

for region-specific grounding

requirements.

3

Place a tag marked DO NOT DISCONNECT on the ground wire at the
electrical panel.

4

Test the ground

Refer to Figure 20 on

page 94

for the NTBK80 Ground Bar

WARNING

A qualified technician or electrician must make the
connection in the AC electrical panel.

Table 12
Region-specific grounding wire requirements

Region

Grounding wire requirements

Germany

#8 AWG (8.36 mm

2

) green/yellow

wire

Other regions in Europe

not smaller than #6 AWG
(13.3 mm

2

) at any point

UK

two green/yellow wires no thinner
than two 10 mm

2