Connections

Connection checklist

Before connecting a Signaling Server, ensure that you have the following
materials on-hand.

Connecting a Nortel CP PM Signaling Server

This section contains instructions for connecting the NTDW61BAE5 CP PM
Signaling Server to the ELAN and TLAN subnets of a CS 1000E and

WARNING

Do not modify or use a supplied AC power cord if it is not
the correct type required for the host region.

IMPORTANT!

Nortel CP PM servers are powered through the backplane of the Media
Gateway, Universal Equipment Module or 11C cabinet into which they
are installed and thus require no power cord.

Table 15
Connections checklist

Have you:

Obtained a serial cable (DTE-DTE null modem cable) to connect the server to a
maintenance terminal?

Obtained the NTAK19EC cable (if you are connecting a Nortel CP PM server)? This
cable adapts the 50-pin MDF connector on the back of the shelf of the Media Gateway,
Universal Equipment Module, or 11C cabinet to a 25-pin DB connector.

Obtained the CAT5 cables (or better) to connect the server to the ELAN and TLAN
subnets?