Electrical Installation 2 - 2

Termination Configuration - Power Wiring

The Circuit Breaker/MCP is located in the upper right hand side of the Bypass unit. The Bypass three phase input power
connection is made to the input terminals of the MCP. See Figure 2.1 and 2.2 for representative examples.

Fig 2.1 Typical Input Power Connection,

Fig. 2.2 Typical Input and Output Power

Wall Mount Unit

Connections, Floor Mount Unit

The OverLoad Relay (OLR) is mounted to the contactor assembly or back panel (depending on rating), just above the bypass
contactor. The Bypass three phase output power connection to the motor is made to the output terminals of the OverLoad
Relay. See Figure 2.3 for representative examples.

Fig 2.3 Typical Output Power Connection, Wall Mount Units

Overload Relay

Motor Connections

Input Power

Ground Lug

Ground Lug

Input Power

Motor
Connections

Motor Connections