Electrical Installation 2 - 14

!

Wiring Checks

After all wiring is completed, perform the following checks:
1.

Is all wiring correct?

2.

Have all wire clippings, screws or other foreign material been removed from the Drive and Bypass enclosure?

3.

Are all terminal screws tight?

!

Control Circuit Wiring Precautions

Observe the following precautions when wiring control circuits:
1.

Separate control wiring from power/motor wiring and other high-power lines.

2.

Separate wiring for control circuit terminals for digital outputs from wiring to other control circuit terminals.

3.

If using an optional external power supply, it should be a UL Listed Class 2 power supply source.

4.

Use twisted-pair or shielded twisted-pair cables for control circuits to prevent operating faults. Prepare cable ends as
shown in Figure 2.10.

5.

Connect the shield wire to terminal E(G).

6.

Insulate the shield with tape to prevent contact with other signal lines and equipment.

Fig 2.10 Preparing the Ends of Shielded Twisted-Pair Cables

Table 2.5 Terminal Numbers and Wire Sizes (Same for all Bypass Units)

Terminals

Terminal

Screws

Tightening

Torque

lb.-in.

(N•m)

Possible

Wire Sizes

AWG

(mm

2

)

Recommended

Wire Size

AWG

(mm

2

)

Wire Type

DRIVE

TERMINALS:

FM, AC, AM, SC, SN,

SP, A1, A2, +V, S1, S2,

S3, S4, S5, S6, S7, MA,

MB, MC, M1, M2, M3,

M4, MP, R+, R-, S+,

S-, IG

TB1 ON PCB A2

TERMINALS:

TB1-1 through TB1-26

Phoenix

type *3

4.2 to 5.3

(0.5 to 0.6)

Stranded

wire:

26 to 16

(0.14 to 1.5)

18

(0.75)

• Shielded, twisted-pair wire

*1

• Shielded, polyethylene-covered,

vinyl sheath cable

E(G)

M3.5

7.0 to 8.8

(0.8 to 1.0)

20 to 14

(0.5 to 2

*2

)

12

(1.25)

*1. Use shielded twisted-pair cables to input an external speed command.

*2. We recommend using straight solderless terminals on digital inputs to simplify wiring and improve reliability.

*3. We recommend using a thin-slot screwdriver with a 3.5 mm blade width.

Shield sheath

Insulation

Connect to shield sheath
terminal E(G) at Drive

Insulate with tape

Do not connect here.