I N S T A L L A T I O N

Routing Cables

Version 2

Model 200iP/250iP Motorcycle Pit Dynamometer Installation Guide

2-19

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

ROUTING CABLES

The following instructions show the support arm and control panel mounted on the
right side of the dyno with the Control Panel Interface (CPI) and dyno electronics on
the left side of the dyno.
The CPI and dyno electronics must be placed near the conduits in the pit.
Be sure to keep the power and communications cables in different pit conduits. For
the following instructions, we will designate the pit conduits as shown in Figure 2-21.

Figure 2-21: Pit Dyno Room Layout

PD026A

dyno

electronics

control panel

interface

(CPI)

control panel

junction box

monitor support and tray

route communications cables

in designated conduit

route power cables

in designated conduit