Lift dryer, Chapter 9 lift dryer, Steps to lift dryer – Grain Systems PNEG-707GSI User Manual

Page 109: Vertical channel splice, Universal shim plate, Safety check before each lift

Advertising
background image

PNEG-707 12', 18', 24' and 30' GSI Commercial Tower Dryer

109

9. Lift Dryer

See Orientation Section on Page 19

for dryer dimensions, components, wall sheet guidelines, etc.

See Appendix A on Page 435

for tools and equipment,

Appendix B on Page 437

for hardware, etc.

Steps to Lift Dryer

Vertical Channel Splice

Splice vertical channels together with vertical
channel splices.

Use 3/8" x 1" galvanized steel bolts and nuts.

Figure 9A Vertical channel splice, 10 gauge.

Universal Shim Plate

To level dryer, shim dryer legs with universal shim
plates. Use universal shim plates only for leveling
jacks and completed dryer.

Figure 9B Universal shim plate. Use only for leveling

jacks and completed dryer.

Important Safety Precautions:
Dryer has sharp edges. These sharp edges may cause serious injury. Use
appropriate personal protective equipment. Use proper lifting techniques.

Safety check before each lift.

Tighten all bolts on dryer (except lower ladder parts).

Check for clearance from existing power lines, equipment and structures.

(See Orientation Section on Page 19.)

Do not lift dryer when it is windy enough to shift jacked dryer.

Move next set of vertical channels near to dryer, and pre-install vertical channel
splice to them.