19. Tower Base

PNEG-707 12', 18', 24' and 30' GSI Commercial Tower Dryer

207

Vertical Base Channel Right and Left Kits

Install R.H. vertical base channels and L.H. vertical base channels to bottom of vertical channel columns.

Bottom of vertical base channel is angled. Attach short side of vertical base channel to jig clip with jig clip
extender.

(See Figure 19E.)

Kits designed to shorten jack lift, improve safety.

Outside Solid Wall Sheets

Last ring of outside wall sheets and inside wall sheets on dryer are solid.

See Orientation Section on

Page 19

for assembly layout for placement.

Install outside solid wall sheets at base of dryer.

NOTE: After compression angle weldment is installed in later step, install inside solid wall sheets at base

of dryer.

Sealing Strip

Bolt sealing strip

(See Figure 19F and

Figure 19G.)

to bottom of outside solid wall sheets.

Use 5/16" x 3/4" whiz lock bolts and nuts.

Figure 19D

Figure 19E Use jig clips extenders (arrow) to

attach vertical base channel to jig clip.

Figure 19F Sealing Strip

Figure 19G Sealing strip (arrow) is installed

to bottom of outside solid wall sheets.

A

B

A. R.H. Vertical base channel
B. L.H. Vertical base channel

Top

Top

Bottom

Bottom

(Kit generally comes with 3 pieces and hardware.)