Caulking – Grain Systems PNEG-707GSI User Manual

Page 220

Advertising
background image

20. Cool Section Floor

220

PNEG-707 12', 18', 24' and 30' GSI Commercial Tower Dryer

Caulking

After hopper and metering drum are installed, run a bead of silicone injection caulking around (top)
outside edge hopper. Fill gaps between cool section and inside wall of dryer.

A good seal is important to reduce dust in cool section.

Figure 20B Moving metering drum into center of dryer.

Figure 20C Caulking outside edge of hopper.